| Project Date | : | 2006 - 2014 |
| Steel Manufacturing | : | 15.000 Tons |
| Steel Assembly | : | 15.000 Tons |
| Cooling Water Pipes | : | 35.000 m |
| Electric Arc Furnace Mechanical Installation | : | 2.500 Tons |
| Filter Assembly | : | 2.500 Tons |
| Slab Building Assembly | : | 3.500 Tons |
| Continuous Building Assembly | : | 2.750 Tons |
| Water Facilities Piping | : | 5.800 m |
| Oxygen Plant Mechanical | : | 2.000 Tons |
| Facade Roof Cladding | : | 58.500 m² |